SURETY
RELET / TAKEOVER WORK Over
the past sixteen years we have been involved in relet projects for
completion and/or repair ranging in size from $75,000.00 to more than
$5,700,000.00. Our work has run the spectrum from acting as a General
Contractor and/or construction manager all the way to completing the
installation of the exterior curtain wall on the $180,000,000.00 Orange
County Courthouse in Orlando, FL. We have operated on a fixed sum basis as
well as on a cost plus or as a cost plus with a guaranteed maximum. We
are proud to say that on all occasions that we either contracted with the
surety for completion and/or repair or were tendered to the obligee for
completion and/or repair. Not once has there been any additional
complaints from these obligees. The projects were sold and accepted without
complications. We
also stand ready to submit a fixed cost proposal on a project and agree to
perform with a bond and a warranty. If the obligee and surety proceed to
litigation and if this work is not awarded to us, we stand ready to
testify regarding the cost to complete. Landmark
has personnel that understand the special, and often unusual, aspects of
surety work, and we're
routinely
called upon to travel throughout the Eastern United States to assist with
the completion of those projects. Here are a few surety projects that we have completed: Orange
County Courthouse Orlando,
Florida The
overall project is a 25 story high rise with three adjacent buildings.
Total construction The
completion cost of our portion of the work was approximately $5,600,000.00 Surety
Company - SF&G/St. Paul Surety
Company Representative - Mr. Greg Daily (410 205-0492) Gatlinburg
Towers Condominium Project Gatlinburg,
TN This project consisted of the completion of a seven story building containing 40 condominium units and three penthouses. Completion Cost - Approximately $1,000,000.00 Surety Company - Universal Surety Company of America Surety Company Representative - Mr. Mike Franks, Esq. (615 742-9308)
Fort
Bragg Brigade Barracks Revitalization Fort
Bragg, North Carolina The overall project was a
$85,000,000.00 housing complex for a portion of the 82nd Airborne
Division. After the electrical subcontractor defaulted, we were asked to
arrange for and supervise the completion of the electrical and fire
alarm portions of the general contract. Completion Cost of the electrical work
was $5,700,000.00 Surety Company - USF&G/St. Paul Surety Company Representative - Mr.
James Gibson (610 832-8249). Now employed by
Liberty Mutual Highland
Commons Shopping Center Boone,
North Carolina Completion Cost $1,250,000.00 Surety Company - CNA Surety Company Representative - Mr.
Robert Colby, (770 984-9319)
Washington
County Jail Jonesborough,
TN The overall project was a $9,000,000.00
detention facility. We were asked to complete the electrical and security
portions of the work after the electrical contractor defaulted. The Completion Cost of our portion of
the work was $1,155,000.00 Surety Company - USF&G Surety Company Representative - Mr.
James Gibson (610 832-8249) Lincoln
County Landfill Closure Fayetteville,
TN This
project involved completing the excavating, site drainage and landscaping
portion of a landfill closure project after the General Contractor was
terminated. The
completion cost of our portion of the work was $285,000.00 Surety
Company Representative - Mr. John Gillum (615 742-9319 Comfort
Inn Lenoir
City, TN This
project consisted of the completion of a three story Comfort Inn after the
General Contractor defaulted. The owner cashed out with the surety company
and retained us to complete the project. The
completion cost of our portion of the work was $525,000.00. Owner’s Representative - Mr. Chetan Patel (423 988-8880) Remedial
Repair Work to Warehouses Memphis,
TN This
project involved completing substantial corrective work (welding, cable
bracing, bolting, etc.) to 2,000,000 square feet of existing metal
buildings while the tenants conducted their normal business activities.
The project was originally scheduled to be completed in 7 months. We were
able to complete the work in less than 3 months and $680,000.00 under
budget. Completion
Cost - approximately $425,000.00 Owner’s
Representative - Mr. Al Richey (800 777-9378) Repairs
to existing warehouse/production facility Permna Color Cleveland,
TN The
overall project was 100,000 sq. ft. warehouse/production facility.
Portions of the underlying soil were improperly compacted resulting in the
settlement/cracking of portions of the concrete floor slabs. We were asked
to remove the concrete/replace the soil/replace the slab as well as
complete other more extensive warranty work. We completed this work while
the production facility remained in operation. The
Completion Cost of our portion of the work was $325,000.00 Surety
Company - Great American Insurance Company Surety
Company Representative - Mr. John Gillum (615 742-9319) Industrial
Coating Applications University
of North Carolina; Chapel Hill The overall project was a
$75,000,000.00 steam generation facility that supplies heat to the entire
UNC campus. The completion cost of our portion of
the work was $578,000.00 Surety Company - Balboa Insurance
Company Surety Company Representative - Mr. Sam
Poteet (615 742-9321) Hemlock
Park Area Sewer Extension Service City
of Kingsport Kingsport,
TN The
overall project consisted of the installation of more than four miles of
water and sewer lines, pump station and supporting structures. At the time
that we were asked to complete the project, it was about 45% complete. Completion
Cost $1,200,000.00 Surety
Company - Balboa Insurance Company Surety
Company Representative - Mr. Mike Franks
(615 244-0030) |
||||||||||||||